• Update: New Circle Rd & Alexandria Drive Construction

    The Kentucky Transportation Cabinet, Department of Highways, announces an update for New Circle Road construction. Bridge demolition work at this time is complete. Construction for the bridges will be ongoing inside the barrier wall. Blasting operations will be in effect for Wednesday, January 14. Wednesday, Jan. 14 Approximate blasting times: 9:00 a.m....

  • Weather Advisory – Freezing Drizzle and Black Ice

    The National Weather Service in Louisville has issued a Travelers’ Advisory for freezing drizzle and black ice, which is in effect from 9pm this evening until 9am Tuesday morning. Rain showers will transition to drizzle this evening, and as temperatures drop below freezing, freezing drizzle could cause slick and icy spots to...

  • New Circle Road Construction Continues this Weekend

    The Kentucky Transportation Cabinet, Department of Highways, announces that the work for Friday and Saturday on northern New Circle Road has been rescheduled due to weather temperatures. The closures are necessary for bridge demolition operations to be completed. Saturday, Jan. 10 – 7:00 p.m. to 5:00 a.m. Sunday, Jan. 11 The left...

  • Lane Closures on I-75 Southbound

    Per the Kentucky Transportation Cabinet, brush removal operations are scheduled to begin tomorrow on Interstate 75. Where: I-75S at mile point 99 (Clay’s Ferry Bridge), continuing south into Madison County. When: January 7th through March 31st, 7:30am through 6:00pm weekdays. Impact: Lane closures as needed, with at least two lanes remaining open...

  • Overnight New Circle Road Stoppages Planned for Construction

    The Kentucky Transportation Cabinet, Department of Highways, announces that closures will be in effect this week for New Circle Road/KY 4. The closures are necessary for bridge demolition work to be completed. Tuesday, Jan. 6 – 7:00 p.m. to 5:00 a.m. Wednesday, Jan. 7 The left lane of the inner loop will...

  • New Circle Road Construction Schedule – Dec. 15

    Construction work continues on north New Circle Road. Here’s what’s new for December 15 – 19. Blasting work will be in effect for New Circle Road (both inner and outer loops) and Old Frankfort Pike.  The mobile operation with traffic stops is scheduled for approximately 9:00 a.m., 10:30 a.m., 12:00 p.m. (noon)...

  • New Circle Road Construction/Blasting Update

    Starting Wednesday, December 10th, and continuing through at least Sunday, December 14th, blasting will occur twice daily on New Circle Road at Old Frankfort Pike, at approximately 10:00am and 1:30pm. New Circle and Old Frankfort will be closed 10 minutes before each blast and remain closed until 10 minutes after each blast....

  • Traffic Advisory: Long-Term Impact to New Circle Road

    The Kentucky Transportation Cabinet launched a major construction project on New Circle Road last night. This project will affect New Circle from Versailles Road to Leestown Road until at least September 30, 2015. The work will include widening of the road, demolition and construction of bridges, and reconfiguration of the interchanges. Expect...

  • Traffic SITREP #5

    Versailles Road is open between Man O’War Boulevard and New Circle Road (both inbound and outbound). The only remaining closure is the ramp onto the outer loop of New Circle.

  • Traffic SITREP #4

    From our partners at the Lexington Traffic Management Center, here’s the latest on the situation with Versailles Road (US 60) between New Circle Road and Man O’War Boulevard: Versailles Road will remain closed in both directions until 7pm or 8pm. Outbound traffic diverts to either direction of New Circle Road (see map)....